Handover and Transition

Handover

The Project Development Agreement states that Crossrail shall manage and deliver the Crossrail Project in a manner that will oblige the operators to accept Handover of assets and systems.

Close collaboration is required to enable successful handover and commissioning of the end-to-end railway. With this in mind, a handover strategy document was co-authored by Crossrail with the operator organisations – Rail for London (RFL) and London Underground (LU).

The handover strategy defines a comprehensive and complete handover as consisting of 7 key deliverables and activities as shown below:

  1. Accountabilities change: RfL and LU accept the transfer of accountability for the management and maintenance of Crossrail infrastructure
  2. Works are complete: as per the contracts, LU and RfL inspections completed, remaining snags documented with agreed close out plan, and all required spares and specialist plant and equipment are available.
  3. Handover documentation: transferred to RfL and LU to support the assurance evidence, operations & maintenance activities, RfL and LU asset databases are populated and ready to use, LU / RfL will receive data from Crossrail before Handover to enable and manage the progressive population of their databases.
  4. All necessary agreements in place: Commercial, Land & Property, Undertakings & Assurances, regulatory Approvals, Licences are transferred to RfL and LU.
  5. Warranties and defect liabilities: Relevant defects rectification and/or warranty provisions are transferred to RfL and/or LU together with documentation defining known defects
  6. Complete Training: Crossrail has successfully delivered to RfL and LU complete training and familiarisation to the required level to enable RfL and LU readiness for Handover.
  7. RfL and LU readiness: RfL and LU has demonstrated readiness to accept the assets (both maintenance and operational).

The handover Strategy and Plan are aligned with the TfL Pathway guidance and the overarching document to be used for Handover to RfL and LU will be the Element Completion and Handover Report (ECHR). This has been derived from the Completion and Consent to Operate Report as detailed in LU Assurance Standard S1538 clause 3.20 and amended to provide a document suitable for Crossrail.

The Handover learning legacy will review the approach to handover following completion of the works including associated learnings for future projects. A further learning legacy paper will detail how the Commissioning & Handover Team monitors the overall progress of Testing & Commissioning route wide and across the individual Stations, Portals & Shafts, including methodology (working level procedure) and tools used to provide consistency, track and report overall project testing and commissioning progress to the Programme Delivery Board.

Transition

Crossrail is being delivered through a special purpose project delivery organisation (which is a subsidiary of TfL and has joint TfL and DfT sponsors) and hence there is a need to wind down this ‘pop-up client’ and to manage the integration of Crossrail into the TfL business.

Early planning can ensure that the smooth handover to operations is accompanied by planned and effective management of the risks and opportunities arising from project close-down and absorption of Crossrail Ltd. in to TfL.  Transition risk (in its broadest meaning) has already been significantly mitigated through the strategy to open Crossrail in stages and through the project team and operators working together to achieve a successful handover and to mitigate the risks of each opening stage.

The Transition Strategy therefore focuses on the risks and opportunities arising from demobilisation of the project and integration with TfL.  A key risk is the unplanned loss of project resources; and the main opportunity is to secure future benefit from the project’s investment in intangible assets (people, processes, information and systems).  In response to this, Transition planning covers changes to governance; transfer of support functions; capture of project information; and retention of talent for TfL and others’ future benefit.

Given the importance of achieving a smooth transition, Crossrail started to develop its strategy and plan when the project was around 60% complete. The Transition Strategy will be shared as part of the learning legacy for the benefit of any organisation that has, or is considering, setting up a similar special purpose project organisation; and a paper discussing the transition experience to date will be made available as the project moves towards its main opening stage, and updated as the project nears final completion.  Further information on transition of governance arrangements from a wholly-owned subsidiary but with fully independent Board to a legal entity retained within TfL will be included in later versions of the paper or published as a separate learning legacy.

Handover and Transition documents:

Summary Publication date Document Type

Information Handover Principles

Topic area: Information Compliance

Previous examples of large railway infrastructure projects have been handed over to the infrastructure managers with supporting information presented in paper and CD-ROM format. This paper will describe the innovative approach that Crossrail took to creating a Digital Railway while the Physical Railway was constructed....

26/02/2016 Case Study
Document type: case study

Enabling Quality Asset Information

Topic area: Asset Information

(Future release)

Frequently on engineering projects, the acquisition of asset information is undertaken shortly before handover, leading to poorer quality asset information and more expensive data gathering activities post-handover. The Crossrail Technical Information Department is proactively ensuring that timely, good quality asset i...

31/03/2018 Case Study