Handover and Transition

Handover

The Project Development Agreement states that Crossrail shall manage and deliver the Crossrail Project in a manner that will oblige the operators to accept Handover of assets and systems.

Close collaboration is required to enable successful handover and commissioning of the end-to-end railway. With this in mind, a handover strategy document was co-authored by Crossrail with the operator organisations – Rail for London (RFL) and London Underground (LU).

The handover strategy defines a comprehensive and complete handover as consisting of 7 key deliverables and activities as shown below:

  1. Accountabilities change: RfL and LU accept the transfer of accountability for the management and maintenance of Crossrail infrastructure
  2. Works are complete: as per the contracts, LU and RfL inspections completed, remaining snags documented with agreed close out plan, and all required spares and specialist plant and equipment are available.
  3. Handover documentation: transferred to RfL and LU to support the assurance evidence, operations & maintenance activities, RfL and LU asset databases are populated and ready to use, LU / RfL will receive data from Crossrail before Handover to enable and manage the progressive population of their databases.
  4. All necessary agreements in place: Commercial, Land & Property, Undertakings & Assurances, regulatory Approvals, Licences are transferred to RfL and LU.
  5. Warranties and defect liabilities: Relevant defects rectification and/or warranty provisions are transferred to RfL and/or LU together with documentation defining known defects
  6. Complete Training: Crossrail has successfully delivered to RfL and LU complete training and familiarisation to the required level to enable RfL and LU readiness for Handover.
  7. RfL and LU readiness: RfL and LU has demonstrated readiness to accept the assets (both maintenance and operational).

The handover Strategy and Plan are aligned with the TfL Pathway guidance and the overarching document to be used for Handover to RfL and LU will be the Element Completion and Handover Report (ECHR). This has been derived from the Completion and Consent to Operate Report as detailed in LU Assurance Standard S1538 clause 3.20 and amended to provide a document suitable for Crossrail.

The Handover learning legacy will review the approach to handover following completion of the works including associated learnings for future projects. An engineering paper details the Integrated Testing & Commissioning across the project.

Transition

Crossrail is being delivered through a special purpose project delivery organisation (which is a subsidiary of TfL and has joint TfL and DfT sponsors) and hence there is a need to wind down this ‘pop-up client’ and to manage the integration of Crossrail into the TfL business.

Early planning can ensure that the smooth handover to operations is accompanied by planned and effective management of the risks and opportunities arising from project close-down and absorption of Crossrail Ltd in to TfL. Transition risk (in its broadest meaning) has already been significantly mitigated through the strategy to open Crossrail in stages and through the project team and operators working together to achieve a successful handover and to mitigate the risks of each opening stage.

The Transition Strategy therefore focuses on the risks and opportunities arising from demobilisation of the project and integration with TfL. A key risk is the unplanned loss of project resources; and the main opportunity is to secure future benefit from the project’s investment in intangible assets (people, processes, information and systems). In response to this, Transition planning covers changes to governance; transfer of support functions; capture of project information; and retention of talent for TfL and others’ future benefit.

Given the importance of achieving a smooth transition, Crossrail started to develop its strategy and plan when the project was around 60% complete.

Handover and Transition documents:

Summary Publication date Document Type
Stations Bringing into Use and Handover

Stations Bringing into Use and Handover

Topic area: Handover & Transition

This paper highlights key lessons and recommendations that have emerged through the successful integration, bringing into use and handover of the new central Elizabeth line stations by Crossrail to the Infrastructure Maintainers as end-users.  The paper details the organisational arrangements and tools and techniques ...

18/05/2023 Technical Paper
Completion Readiness Assessment Framework (CRAF) Procedure

Completion Readiness Assessment Framework (CRAF) Procedure

Topic area: Quality

Completion Readiness Assessment – Framework (CRAFs) are Quality assessments geared towards ‘completion activities’ and with pushing Tier 1s and Project Teams to gain NEC3 Contract Completion. These independent assessments are carried out by discipline leads and scrutinise the planning and progress in ...

18/05/2023 Good Practice Document
Crossrail project to Elizabeth line operations: Operational approach and lessons learned

Crossrail project to Elizabeth line operations: Operational approach and lessons learned

Topic area: Operations Management

The delivery of Elizabeth line operations from concept to passenger service has ultimately been very successful. The line is a new type of service in the UK, analogous to the French RER or German S-Bahn systems, and brings together (i) major new infrastructure, (ii) new rules and regulations (as it is a unique railw...

05/04/2023 Journal Publication
Transitioning of the engineering management in the handover phase of programme delivery

Transitioning of the engineering management in the handover phase of programme delivery

Topic area: Systems Integration and Technical Assurance

The Engineering Management Office (EMO) function provides an important link between the client’s specifier of requirements and its contracting arm delivering the works. The longevity, scale and geographical fragmentation often necessitate a phased completion approach in delivery of major infrastructure programmes. Ne...

02/12/2021 Technical Paper
Information Handover Principles

Information Handover Principles

Topic area: Information Compliance

Previous examples of large railway infrastructure projects have been handed over to the infrastructure managers with supporting information presented in paper and CD-ROM format. This paper will describe the innovative approach that Crossrail took to creating a Digital Railway while the Physical Railway was constructed....

26/02/2016 Case Study