Law and Contracts documents:
Summary | Publication date | Document Type |
---|---|---|
Early Warning Notice Contract Procedure: Improving its use on large Infrastructure ProjectsTopic area: Law and Contracts The ‘New Engineering Contract’ (NEC) form of contract launched in 1993 and was a revelation in the construction contracting world, using plain language and built-in processes to stimulate good project management. A key NEC contractual tool is the Early Warning Notice (EWN) procedure which facilitates collaborati... |
18/05/2023 | Research Paper |
Contract Administration ManualTopic area: Law and Contracts The Crossrail programme adopted the NEC3 ECC form of contract with additional conditions of contract (Z clauses). Almost all works contracts adopted the Target Cost payment option (Option C). A Contract Administration Manual was provided to those with delegated contract authority and those involved in supporting the ma... |
17/05/2023 | Good Practice Document |
Crossrail Systems Contract Works Information Part 2BTopic area: Law and Contracts The Works Information sections of the NEC3 Contract documents used by Crossrail consisted of: Part 2A – Particular Works Information – relevant to the individual project Part 2B – General Requirements -requirements that were common to all similar contracts Part 2C – Technical Requirements This... |
15/09/2021 | Good Practice Document |
Crossrail approach to NEC3Topic area: Law and Contracts This paper explains the approach taken to the NEC3 form of contract on the Crossrail project and explains how that approach was established and then implemented. It then identifies some issues which arose out of the form of contract used and a number of improvements which might be considered on future projects. It wi... |
17/07/2018 | Technical Paper |
Crossrail Main Civils Contract Works Information Part 2BTopic area: Law and Contracts The Works Information sections of the NEC3 Contract documents used by Crossrail consisted of: Part 2A – Particular Works Information – relevant to the individual project Part 2B – General Requirements -requirements that were common to all similar contracts Part 2C – Technical Requirements Part... |
17/07/2018 | Good Practice Document |
Crossrail project: commercial aspects of works contracts for London’s Elizabeth lineTopic area: Law and Contracts Choosing the right commercial arrangements between the client and contractors was critical to successful delivery of the £14·8 billion Crossrail project to deliver the Elizabeth line east–west railway across London. This paper explains how delivery organisation Crossrail Limited used the NEC3: Engineering and Cons... |
25/09/2017 | Journal Publication |
Central Communications (CEC) – Improving Formal Communications on a Major ProgrammeTopic area: Procurement A key challenge to a major programme is establishing a mechanism to efficiently communicate information from the centre, down to multiple site teams and into the supply chain. This paper explains how the contract management system was developed to incorporate directions to site times (“CECs”). The CEC process was i... |
18/05/2023 | Micro-report |
Crossrail approach to Contract Completion – The Employer’s Completion ProcessTopic area: Quality This report discusses the approach taken by the Crossrail programme to ensure due diligence before certifying construction contracts as complete under the NEC contract. The Employer’s Completion Process (ECP) was introduced to define all essential checks necessary to achieve completion based on the Works Informat... |
05/05/2023 | Technical Paper |
Crossrail’s Non-Conformance (Defect) Reporting SystemTopic area: Quality The construction industry has historically been reluctant to proactively identify defects due to fear of cost and reputational impact, which unfortunately resulted in latent defects being discovered far too late. Crossrail acted upon lessons learned from the Channel Tunnel Rail Link project and ensured defects were ide... |
20/04/2023 | Technical Paper |
Crossrail cost to complete: Cost and commercial managementTopic area: Commercial Management In August 2018, Crossrail Ltd (CRL) announced that the programme to open the Elizabeth line would not be delivered on the original estimated timeline and that the opening of the Central Operating Section (COS) by December 2018 was not achievable. It was also made public that the original estimated budget would be in... |
05/04/2023 | Journal Publication |
Works Information Study (Supply Chain Quality Requirements)Topic area: Quality The key quality requirements for the supply chain quality included in Crossrail contracts were over and above the industry norm and were intended to ensure that contractors were resourced correctly and established systems to deliver quality. This case study covers the quality resources and systems used in Crossrail... |
26/02/2016 | Case Study |