Cyber Security Management and Assurance | Micro-report |
Crossrail has delivered the first truly digital railway in the UK. To ensure a resilient and reliable Elizabeth line railway, all new delivered system elements; Stations, Shafts, Portals and Routeway systems, need to be ... |
Lee John Allen CEng MIET CMgr MCMI AMIRSE | 18/05/2023 |
Crossrail Project Non-conformance Reporting Data | Dataset |
Non-conformance reports (NCRs) were a key part of Crossrail’s quality management system. They were used to record non-conformities (defects) in the works (product, workmanship, or electronic systems), and provided ... |
Crossrail Ltd | 17/05/2023 |
Instrumentation and Monitoring Close Out Reports | Dataset |
This dataset includes ground movement monitoring close-out reports prepared by Crossrail contractors during tunnelling. These are shared with the aim of assisting better understanding of soil structure interaction and co... |
Crossrail Ltd | 17/05/2023 |
Contract Administration Manual | Good Practice Document |
The Crossrail programme adopted the NEC3 ECC form of contract with additional conditions of contract (Z clauses). Almost all works contracts adopted the Target Cost payment option (Option C). A Contract Administration Ma... |
Crossrail Ltd | 17/05/2023 |
Crossrail Authorisation for Placing into Service – Lessons Learned | Technical Paper |
The Central Operating Section of the Elizabeth line is the first large scale railway project in UK to be built and assessed under the Railway Interoperability and Safety Regulations. The Authorisation for Entry into Pass... |
Maya Petkova BSc CEng FIET FIRSE | 17/05/2023 |
Managing Contractor Self-Certification on Crossrail | Technical Paper |
Based on processes and lessons from High Speed 1, the requirements for Self-Certification were written into Parts 13, 20 and 29 of the Works Information 2B and supplemented with procedures and templates specific to civil... |
Judith Griffiths CQP MCQI | 17/05/2023 |
Design Gates Process | Good Practice Document |
An essential part of the Crossrail design review process involved the completion of both single disciplinary and inter-disciplinary design reviews. This provided an opportunity for interfacing Framework Design Consultant... |
Crossrail Ltd | 11/05/2023 |
System Safety for Complex Projects – The Crossrail Approach | Technical Paper |
This Technical Paper sets out the details of the System Safety approach used by the Crossrail Project and describes some of the solutions employed to resolve the key challenges faced during the lifecycle of the project.... |
Hayat Zerkani PhD BSc CEng MIET | 10/05/2023 |
The Importance of Planning in the Production of Construction Deliverable Records | Technical Paper |
Planning with the end in sight is crucial in the delivery of all successful projects, and is especially true in the construction industry, where both the works and personnel involved can change at such a rapid pace. It... |
Chrys Chimarrides CEng MICE | 10/05/2023 |
Crossrail approach to Contract Completion – The Employer’s Completion Process | Technical Paper |
This report discusses the approach taken by the Crossrail programme to ensure due diligence before certifying construction contracts as complete under the NEC contract. The Employer’s Completion Process (ECP) was i... |