Programme Controls

The Programme Controls Team set out to develop a world-class controls function which, through robust reporting and sound programme management protocols, would support the Crossrail programme to deliver the works safely and to time, specification and cost. To this end, the Controls function was built on four key principles. These were to:

  1. Set the standards: Provide the definition of processes and procedures to be adhered to throughout the programme;
  2. Provide integrated information: Provide decision makers and members of the Executive, the Board and the Sponsors with reliable and timely information on the current and projected status of the programme;
  3. Bring foresight and advice: Provide programme level analysis and insight based on interpreting project level data; and
  4. Provide assurance: Support the management and control of the delivery costs, schedule and performance objectives for the whole programme to minimise risk of failure.

Through the delivery of the core base services of planning, cost management, risk management, programme change management and reporting, the ambition has been met, and continues to evolve as Crossrail heads into the final delivery phase. These learning legacy pages seek to share the processes, systems and some templates with the direct intention of helping others establish an approach that delivers effective but efficient programme controls. Below are some of the key lessons that have been learned to date, including:

  1. Obtaining agreement on the work breakdown structure and implementing it with zero tolerance;
  2. The use of Primavera P6 for planning and nothing else;
  3. Keeping the Controls community out of too much detail;
  4. Starting formal programme performance reviews early;
  5. Produce the best management reports you can;
  6. Reinforcing the culture to build confidence.

Crossrail benefited from the lessons of the London 2012 Olympic and Paralympic Games. Through shared information, Crossrail has maintained simplicity at the heart of its approach. Examples such as the Planning and Scheduling Handbook and the industry leading approach to Performance Management, the use of Earned Value and, later on, Earned Schedule, are all areas of relevance to future projects and programmes.

Crossrail Head of Programme Controls, Richard Palczynski explains Crossrail’s approach to programme controls in this webinar:

Programme Controls Documents:

Summary Publication date Document Type
Crossrail Programme Recovery

Crossrail Programme Recovery

Topic area: Programme Controls

In early 2020, following the 2018 announcement of significant delay to the opening of Crossrail and the associated cost increases, the Crossrail programme was hit by yet another blow – COVID-19. The programme stopped all work in March 2020 and set about developing a recovery strategy to achieve the original object...

05/04/2023 Journal Publication
Crossrail programme organisation and management for delivering London’s Elizabeth line

Crossrail programme organisation and management for delivering London’s Elizabeth line

Topic area: Programme Controls

The Crossrail Act for an east–west railway across London was given royal assent in 2008 and construction started on what will become the new Elizabeth line in 2009. This paper looks at how Crossrail Limited, the client delivery organisation, was assembled, how it evolved and what programme and project management prac...

19/09/2017 Journal Publication
Commercial Assurance Reporting

Commercial Assurance Reporting

Topic area: Programme Controls

A programme controls approach was needed to integrate commercial management information, to support decision making at the programme and sector level. Periodic Programme Controls Working Group meetings, combined with data and trend analysis, facilitated a good understanding of commercial performance across each of the ...

26/02/2016 Micro-report
Completing the Elizabeth line – Session 1 – Project and Programme Management

Completing the Elizabeth line – Session 1 – Project and Programme Management

Topic area: Completing the Elizabeth line event presentations

03/05/2023 Video
Fair Payment and Project Bank Accounts

Fair Payment and Project Bank Accounts

Topic area: Cost Control

This paper describes the use of Project Bank Accounts on the Crossrail project to encourage fair payment and protect subcontractors. It would be of interest to any project looking to ensure they set up processes to pay their contractors and sub-contractors fairly and in a timely manner, in line with best practice as re...

09/07/2018 Micro-report
Defined Cost Verification at Crossrail

Defined Cost Verification at Crossrail

Topic area: Cost Control

This paper outlines both process and `ethos` of Schedule of Cost Component(SoCC) Cost Verification activity on the Crossrail Programme. The paper outlines how the Cost Verification function provides both, assurance that the Contractors financial systems and controls are aligned to Works Information requirements, and to...

09/07/2018 Micro-report
Initial Control Baseline and Review Points

Initial Control Baseline and Review Points

Topic area: Cost Control

This paper explains Crossrail’s response to the Government’s 2010 Comprehensive Spending Review, which instigated a comprehensive value management exercise to optimise the programme. This lead to increased sponsor confidence in Crossrail’s affordability, leading to the issue of a Positive Project Revi...

09/07/2018 Micro-report
Implementing Risk Management at Crossrail

Implementing Risk Management at Crossrail

Topic area: Risk Management

The robust management of risk has played a significant part in the delivery of Crossrail. This case study explains the approach to risk management that was adopted, the rationale behind it and the outcomes that were experienced. It covers all aspects of risk management in Crossrail and how risk management was integrate...

13/03/2018 Case Study
Quantitative Cost Risk Assessment

Quantitative Cost Risk Assessment

Topic area: Risk Management

This document briefly sets out some key features of how Quantitative Cost Risk Analysis (QCRA) has been undertaken on Crossrail. The main focus of this report is on Crossrail’s approach to QCRA which has a degree of originality in comparison to other major projects, particularly in relation to the trend management pr...

13/03/2018 Micro-report
Render of a Class 345 train within a wireframe render of a station platform

Managing Risk In The Later Stages of Crossrail

Topic area: Risk Management

In order to support delivery during the latter stages of the Crossrail programme there were a number of changes made to the risk management resources and processes. This paper focuses on the key changes that were made from 2015 to take the programme to completion. It will be of interest to any projects and project risk...

13/03/2018 Micro-report
Managing Schedule Risk

Managing Schedule Risk

Topic area: Risk Management

This document briefly sets out some key features of how schedule has been managed and undertaken by Crossrail. The main focus is on Crossrail’s approach to Quantified Schedule Risk Analysis (QSRA) which has a degree of originality, particularly in relation to schedule size and schedule features. This report would be ...

13/03/2018 Micro-report
Programme Efficiency and Cost Reduction During the Delivery Phase

Programme Efficiency and Cost Reduction During the Delivery Phase

Topic area: Reporting

Crossrail is committed to safely deliver a world class railway, on time, and at the lowest possible cost. It is required of all involved in the delivery and management of the programme to drive efficiency and maximise value for money. In 2015, the Crossrail leadership team agreed cost reduction targets with key project...

14/03/2017 Micro-report
Engaging the Supply Chain in Risk Management

Engaging the Supply Chain in Risk Management

Topic area: Risk Management

Managing risk and uncertainty was identified as being a critical element from the start of the Crossrail project. The size, complexity, nature of the works, and ‘thin client’ operating model resulted in a requirement to extend risk management into the supply chain. This paper describes the process of doing ...

14/03/2017 Micro-report
Risk and Assurance

Risk and Assurance

Topic area: Risk Management

For Crossrail Risk and Assurance played a key role in keeping the organisation on track and within its project delivery targets. As a public sector funded project, Crossrail has to provide assurance to a number of external bodies in relation to its governance and effectiveness of delivery. This paper describes its appr...

14/03/2017 Micro-report
Strategic Risk Management

Strategic Risk Management

Topic area: Risk Management

From an early stage of the project, managing risk and uncertainty was identified as being critical to the successful delivery of the Crossrail project. The project’s senior management were strongly supportive and actively engaged in implementing the risk management process, which facilitated the creation of a dedicat...

14/03/2017 Micro-report
Programme Controls Webinar – Commercial Assurance

Programme Controls Webinar – Commercial Assurance

Topic area: Programme Controls Webinar Series

This was the seventh in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management hosted by our partners at the APM. This was the final webinar of the series. The scope of Commercial Assurance spans across the Crossrail Programme, with a particular focus on contracts where Crossrail ha...

15/11/2016 Video
Board Reporting

Board Reporting

Topic area: Reporting

Effective reporting is a result of many separate elements of the Crossrail machine working in harmony to transfer understanding rather than transmit information. To do this in a timely and effective way requires supporting systems and structures and for the value of the outputs to be recognised across the Programme. Th...

24/10/2016 Case Study
Programme Controls Webinar- Performance Assurance

Programme Controls Webinar- Performance Assurance

Topic area: Programme Controls Webinar Series

This was the sixth in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management hosted by our partners at the APM. A key challenge for Crossrail and its stakeholders was to create a mechanism for assuring that Tier 1 contractors were collectively performing at a level that would enable...

19/10/2016 Video
Reporting Procedures Handbook

Reporting Procedures Handbook

Topic area: Reporting

The purpose of this handbook is to outline the reporting procedures at Crossrail for producing, issuing and amending progress reports on the programme. It provides information targeted at 3 key groups: Sponsor, Board, Executive or Crossrail Function members – providing a high level overview of how reporting is carri...

27/09/2016 Good Practice Document
The Planning and Scheduling Handbook

The Planning and Scheduling Handbook

Topic area: Planning

Crossrail Planning and Scheduling Handbook The Planning and Scheduling handbook describes how planning is undertaken at Crossrail. It is an intranet based tool that pulls together the various guidance notes and desktop instructions into one page through a series of linked documents as shown below. This handbook is shar...

27/09/2016 Good Practice Document
Change Control Process

Change Control Process

Topic area: Change Management

This micro-report describes the process Crossrail used to control change to the Baseline of scope, cost and schedule at Programme level.

27/09/2016 Micro-report
Contingency Management

Contingency Management

Topic area: Change Management

This micro-report describes how contingency budgets were established, delegated and managed by Crossrail, and the different categories of contingency budget. It explains the link between contingency and risk management, and control systems.

27/09/2016 Micro-report
Cost Management and Forecasting Procedure

Cost Management and Forecasting Procedure

Topic area: Cost Control

This procedure is an integral component to the Crossrail Controls approach and toolset, and applies to all functional departments in the Crossrail Programme responsible for managing and reporting cost. This procedure details the systems, processes, procedures and tools required to identify, collect, integrate and analy...

27/09/2016 Good Practice Document
Programme Baseline Control

Programme Baseline Control

Topic area: Change Management

This micro-report describes the process to establish the Crossrail Programme Baseline and the components of the Baseline, including the high level Work Breakdown Structure.

27/09/2016 Micro-report
Work Breakdown Structure

Work Breakdown Structure

Topic area: Cost Control

This micro-report gives an overview of how the work breakdown structure (WBS) has been developed and how it is maintained and controlled across the Crossrail programme through the Cost Management System (PRISM). It will be of interest to all those delivering major and complex projects.

27/09/2016 Micro-report
Health and Safety Performance Index (HSPI )

Health and Safety Performance Index (HSPI )

Topic area: Health and Safety improvements

The Health and Safety Performance Index (HSPI) is Crossrail’s leading indicator measurement programme, focussed on Crossrail’s 6 Target Zero Pillars, which are considered the foundation for good health and safety management.  These are; Leadership & Behaviour; Design for H&S; Communications; Workplace Heal...

27/09/2016 Case Study
Estimating Procedure

Estimating Procedure

Topic area: Cost Control

This document sets out the role of the Programme Controls Estimating Team and the procedures and approach undertaken in the preparation of estimates and other activities that were identified as being the responsibility of the estimating team. This procedure applies to the central estimating team and identifies the inte...

27/09/2016 Good Practice Document
Risk Management Plan

Risk Management Plan

Topic area: Risk Management

Managing risk and uncertainty is vital to the successful delivery of Crossrail. This Risk Management Plan describes the activities, governance, roles, responsibilities and process which are required to ensure that Crossrail manages its risks effectively. It forms part of a consistent suite of documentation which descri...

27/09/2016 Good Practice Document
Risk Management Policy

Risk Management Policy

Topic area: Risk Management

Managing risk and uncertainty is critical to the successful delivery of Crossrail. This Risk Management Policy was put in place to ensure that risk management is an integral, visible and consistent part of routine management activity across the programme. It also outlines how effective risk management can support progr...

27/09/2016 Good Practice Document
Quantitative Risk Assessment Procedure

Quantitative Risk Assessment Procedure

Topic area: Risk Management

The purpose of this procedure is to set out how Quantitative Risk Assessment (QRA) is undertaken on Crossrail. It represents a quality plan for achieving Crossrail risk management objectives. It is written to accord with the: Crossrail Risk Management Plan Crossrail Risk Management Procedure Change Control and Budget ...

27/09/2016 Good Practice Document
Commercial Assurance Procedure

Commercial Assurance Procedure

Topic area: Commercial Assurance

This document sets out the agreed process for operating Crossrail’s Commercial Assurance Function. The purpose is to provide a clear and consistent overview of: the vision for Commercial Assurance the process of operating Commercial Assurance accountabilities for the implementation of Commercial Assurance The scope...

27/09/2016 Good Practice Document
Programme Controls Webinar – Risk

Programme Controls Webinar – Risk

Topic area: Programme Controls Webinar Series

This was the fifth in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management hosted by our partners at the APM. From an early stage Crossrail recognised that managing risk was critical to the success of the programme. Crossrail implemented risk management across the organisation wit...

22/09/2016 Video
Programme Controls Webinar – Planning

Programme Controls Webinar – Planning

Topic area: Programme Controls Webinar Series

This was the fourth in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management hosted by our partners at the APM. The Planning function in Crossrail supports the overall delivery and reporting requirements of the business. The planning methodology is detailed in the Planning and Sche...

15/09/2016 Video
Programme Controls Webinar – Change Control

Programme Controls Webinar – Change Control

Topic area: Programme Controls Webinar Series

The third webinar in the series on Crossrail Programme Controls covered the establishment of the programme baseline of scope, cost and schedule, and the process to control change to the baseline at programme level. It described how contingency budgets were established, delegated and managed, and refers to the control s...

01/09/2016 Video
Programme Controls Webinar – Reporting

Programme Controls Webinar – Reporting

Topic area: Programme Controls Webinar Series

This was the second in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management hosted by our partners at the APM. As a high profile, highly complex programme with a large number of internal and external stakeholders, Crossrail has diverse user groups for its management information. T...

28/07/2016 Video
Programme Controls Webinar -Overview

Programme Controls Webinar -Overview

Topic area: Programme Controls Webinar Series

This was the first in a series of Crossrail Learning Legacy webinars focused on Project and Programme Management, hosted by our partners at the APM. This webinar aims to provide an overview of the programme controls put in place on the programme. The Crossrail Programme Controls Team set out to develop a world-class c...

15/06/2016 Video
Performance Assurance Framework

Performance Assurance Framework

Topic area: Audit & Assurance

Crossrail’s approach to performance measurement was based on 6 core areas aligned to corporate objectives, using traditional quantitative based KPIs but supplemented with qualitative based assessments of the supply-chain’s maturity to provide a much richer picture of supply-chain performance.  This enabled the tar...

26/02/2016 Micro-report
Change Control and Budget Management Procedure

Change Control and Budget Management Procedure

Topic area: Change Management

The purpose of this procedure is to define the processes which apply to the control of change and the management of budgets and forecasts. This procedure covers: the Change Management process to establish a methodology for the review, mitigation and approval of all changes from the approved Programme Baseline. This in...

26/02/2016 Good Practice Document
Example Innovation Period Report

Example Innovation Period Report

Topic area: Innovation Programme

Example of a report from the Innovation Programme which fed into the Crossrail period report, describing activities and challenges.

26/02/2016 Good Practice Document
Quality Dashboard

Quality Dashboard

Topic area: Quality

‘Right First Time‘ is a key factor in the success of any project. As part of its quality management process, Crossrail developed a quality dashboard with meaningful metrics that enabled trend analysis and informed decision making to rectify problems and prevent recurrence. This learning legacy page describes the co...

26/02/2016 Micro-report
Crossrail Approach to Earned Value

Crossrail Approach to Earned Value

Topic area: Cost Control

The aim of the Crossrail performance measurement regime was to provide a comprehensive, consistent, timely and reliable view of the programme’s performance that predicted performance, and triggered management action to positively influence the outcome. Earned Value (EV) was one indicator of performance and was used i...

26/02/2016 Micro-report
Crossrail Approach to Estimating

Crossrail Approach to Estimating

Topic area: Cost Control

This report summarises Crossrail’s approach to Estimating, to provide predictability around capital investment and operating costs as well as the critical evaluation of affordability and value for money. This report sets out the role of the Programme Controls Estimating Team, the procedures and approach undertaken as...

26/02/2016 Micro-report
Schedule Reporting

Schedule Reporting

Topic area: Planning

Reporting is a necessary requirement for all projects and developing the methodologies adopted by Crossrail for schedule management and reporting has been key to the success of the programme so far.  This learning legacy paper provides an overview of some of the key principles adopted by Crossrail in the delivery of t...

26/02/2016 Micro-report
Handover and Transition

Crossrail Approach to Managing Interfaces

Topic area: Planning

Identification and definition of interfaces has been critical to the success of Crossrail so far, especially given the number of different Industry Partners involved in delivering the infrastructure.  This learning legacy paper provides an overview of some of the key principles adopted by Crossrail in the delivery of ...

26/02/2016 Micro-report
Key Commodity Monitoring

Key Commodity Monitoring

Topic area: Planning

Crossrail defines a commodity as a measurable piece of work (eg, linear metres of tunnelling, track laying, platform concrete poured etc).  It was recognised that the early identification and monitoring of key commodities was critical to programme success and effective decision making. Undertaking Commodity reporting...

26/02/2016 Micro-report
Crossrail Approach to Managing and Planning Design

Crossrail Approach to Managing and Planning Design

Topic area: Planning

Planning of detailed design is often seen as abstract and difficult to measure progress against.  This learning legacy paper describes how Crossrail, in conjunction with the design gates in the V-Lifecycle (Validation and Verification)  technical assurance process, developed a detailed design programme in P6 and lear...

26/02/2016 Micro-report
Risk Videos

Risk Videos

Topic area: Risk Management

A number of videos have been produced outlining the importance of risk management to Crossrail and also detailing how it is important for the project to consider the risk strategy when working with contractors and the wider supply  chain. Each of the videos are linked below: The importance of Risk Management to the...

26/02/2016 Video
Managing Cost Risk and Uncertainty in Infrastructure Projects

Managing Cost Risk and Uncertainty in Infrastructure Projects

Topic area: Risk Management

In 2015 Infrastructure UK undertook a review of the cost of infrastructure projects in the UK and how this cost could be reduced.  One workstream researched the management of cost risk and uncertainty throughout the project lifecycle, the incentive being to significantly reduce the cost of projects by curbing unnecess...

30/12/2013 Good Practice Document
Cover of ICE Proceedings journal Management, Procurement and Law

Risk Management Critical to Crossrail’s Success

Topic area: Risk Management

Following the positive outcome from the UK government’s 2010 comprehensive spending review, the Crossrail cross-London railway project started awarding its main construction contracts. The author explains how risk management has already benefited the project and why its adoption by the supply chain is critical. Acce...

30/05/2011 Journal Publication
Strategic Risk – A Guide for Directors

Strategic Risk – A Guide for Directors

Topic area: Risk Management

Strategic risk consists of the most important risks that an organisation faces, i.e. the possible future scenarios that would make a material difference (for better or worse) to its ability to achieve its main objectives or even to survive. These risks differ in magnitude from project risks or operational risks, which...

01/05/2006 Journal Publication