Summary
Publication Date
Delivering a Safe Integrated SCL Design: The Challenges and Successes of Crossrail Contract C300/C410

The design delivery for the sprayed concrete linings (SCL) for Crossrail contract C300/C410 Western Running Tunnels and Station Caverns has involve...

03/11/2014
Stabilisation of soil pillar adjacent to Eastern Ticket Hall at Bond Street Crossrail Station

Sprayed concrete lining (SCL) tunnelling alongside the secant pile walls forming the Eastern Ticket Hall (ETH) box at Bond Street station left a na...

03/11/2014
Design and construction of Fisher Street crossover cavern on Crossrail contract C300/C410, London

Creating a complex sprayed concrete lined (SCL) crossover between the Crossrail running tunnels at Fisher Street presented the project team with ma...