Summary
Publication Date
Delivering a Safe Integrated SCL Design: The Challenges and Successes of Crossrail Contract C300/C410

The design delivery for the sprayed concrete linings (SCL) for Crossrail contract C300/C410 Western Running Tunnels and Station Caverns has involve...

03/11/2014
Stabilisation of soil pillar adjacent to Eastern Ticket Hall at Bond Street Crossrail Station

Sprayed concrete lining (SCL) tunnelling alongside the secant pile walls forming the Eastern Ticket Hall (ETH) box at Bond Street station left a na...

03/11/2014
Observed differences in the behaviour of the London Clay sub-units during SCL works for Bond Street Station and Tottenham Court Road Station (C300/410)

Crossrail contract C300/C410 involved the construction of a number of SCL tunnels at Bond Street and Tottenham Court Road Stations, and the Fisher ...

07/09/2015
Use of TBM pilot tunnels for large diameter SCL caverns: the benefits, challenges and successes of Crossrail contract C300/C410

A key bid-winning innovation introduced by BAM Ferrovial Kier (BFK) joint venture on the combined Crossrail Contract C300/C410 was the change of se...

07/09/2015
Management of Obstructions and Adverse Ground Conditions During SCL Tunnelling Works at Bond Street and Tottenham Court Road Stations for Crossrail Contract C300/410

During construction of the sprayed concrete lined tunnels at Bond Street and Tottenham Court Road Crossrail stations, a number of challenging condi...

31/08/2016