Crossrail Lorry Routes | Good Practice Document |
Due to the size and complexity of the Crossrail project, it was decided to try and mitigate traffic issues by liaising with the affected London boroughs from the outset. Approved lorry routes were agreed with each of the... |
Crossrail Ltd | 09/07/2018 |
Biodiversity Accounting Report | Micro-report |
In recognising the importance of understanding biodiversity losses, Crossrail undertook a study to assess and quantify the amount of biodiversity to be lost and gained as a result of development at seventeen of the Cross... |
Lorna Mellings BSc MSc CEnv MIEMA | 09/07/2018 |
Client Advice and Technical Services to Chief Engineer’s Group | Technical Paper |
Between early 2013 and 2018, CEG worked with Crossrail’s programme delivery function and station contractors on station design development and progressive acceptance that requirements were met. In addition, they led th... |
George Stowell BA(Hons) Dipl Arch MA(Dist) MRIAI RIBA, ICE Publishing | 09/07/2018 |
Crossrail Asset Information Guide | Good Practice Document |
Delivering a complete, detailed set of Asset information to support the operations and maintenance of the Elizabeth Line is one of Crossrail’s major challenges. The guide in the document links below provides simple g... |
Crossrail Ltd | 09/07/2018 |
Engineering design of the platform edge screens for the Elizabeth line’s tunnel stations | Journal Publication |
This paper covers the engineering design of the platform edge screens for five Elizabeth line tunnel stations in central London. Full-height platform edge screens are a signature feature of the Elizabeth line’s station... |
Julian Birbeck CEng MIStructE, Rosemary Smiley MEng, George Stowell BA(Hons) Dipl Arch MA(Dist) MRIAI RIBA, Ed Newman-Sanders CEng MICE, The Structural Engineer | 02/07/2018 |
St Giles Circus: meeting the challenges of building above the Elizabeth line | Journal Publication |
The St Giles Circus project involves the £150M redevelopment of a central London site adjacent to Tottenham Court Road Station (Figure 1). The structural and civil engineering design was undertaken by Engenuiti, with ... |
Clive Fussell MEng CEng MIStructE, The Structural Engineer | 02/07/2018 |
A model railway station: implementing a ‘kit of parts’ solution to Custom House – the only above-ground station on the Elizabeth line’s central section | Journal Publication |
The new Elizabeth line station at Custom House was a unique opportunity for design and construction. It is the only above-ground station on the central section of the line and will welcome millions of visitors to London�... |
Ed Newman-Sanders CEng MICE, Rosemary Smiley MEng, The Structural Engineer | 02/07/2018 |
Crossrail’s Key Performance Indicators | Micro-report |
Crossrail established four key objectives on the project: Are we safe? Are we on time? Are we within funding? Are we world class? These four objectives drive all aspects involved in the successful completion of the proje... |
Greg Wazacz CEng MICE MEng | 09/07/2018 |
Construction of the ventilation towers at Tottenham Court Road Elizabeth line station | Journal Publication |
Tottenham Court Road Elizabeth line station is a new station located in the heart of London, adjacent to Oxford Street, being delivered as part of the Crossrail programme. The station is expected to accommodate more th... |
Joseph Maltezos, Tim Harman, The Structural Engineer | 02/07/2018 |
Crossrail’s Information System | Micro-report |
This document describes the core set of processes within a single workflow based Information Management System (IMS) required to support any future major project. It would be of interest to IT professionals looking to su... |